«Preparation of the Design Documentation to Construct the Road on Chakvi-Makhinjauri Section of Senaki-Poti-Sarpi International Road and Implementation of the Rehabilitation Works»
«Preparation of the Design Documentation to Construct the Road on Chakvi-Makhinjauri Section of Senaki-Poti-Sarpi International Road and Implementation of the Rehabilitation Works»
Project: «Preparation of the Design Documentation to Construct the Road on Chakvi-Makhinjauri Section of Senaki-Poti-Sarpi International Road and Implementation of the Rehabilitation Works»;
Client: «GZA» Ltd;
Financed by: The World Bank (WB);
Tasks: Preparation of Ressettlement Action Plan based on the field survey data and in line with the requirements of the WB and Georgian Legislation; Drafting the new cadastre maps; Preparing Inventory of losses; Conducting social survey; Organizing public consultations;
Project completed: July 2, 2018.
 
;